Builder:

T-Power nv

Architect:

Siemens

Study team:

Siemens
Tess Power Tess Power Tess Power Tess Power

Tess Power

Tessenderlo

Main civil works

Description

Construction of the concrete foundations for a power plant.

Timing

Date order 26-03-2009
Date subscription 20-02-2009
Executed by 50% Alg. Aann. Van Laere 50% Democo
Start 15-05-2009
Delivery 17-05-2010

Technical description

- Groundwork
- Formwork
- Reinforcement
- Concrete
- Limited sewerage works

Building physical data

Concrete:13.270 m³
Reinforcement:1.335.200 kg
Formwork:15.000 m²
Labour:52.722 hours
Groundwork - digging:17.618 m³
Groundwork - filling:17.237 m³