Builder:

Federale Overheidsdienst Mobiliteit & Vervoer

Study team:

S.C.E.S nv
NATO – OTAN tunnel NATO – OTAN tunnel NATO – OTAN tunnel

NATO – OTAN tunnel

Evere

Tunnel

Description

Construct a tunnel on site at the crossing for traffic travelling to Brussels city centre

Timing

Executed by 33,3% Alg. Aann. Van Laere nv 33,3% Jan De Nul 33,3% Cit Blaton

Technical description

- Techniques: tunnel technique + traffic technique
- Ventilation
- Lighting
- Fire detection
- Camera
- Underground technical area = 194 m²
- Pump cellar
- Buffer basins RW + catch basins contaminated water = 132 m³
- Emergency power aggregate (NSA)
- Increasing water pressure system