Builder:

Genzyme Flanders

Architect:

ELD Engineering

Study team:

PM Group
Genzyme Flanders – Project Stella Genzyme Flanders – Project Stella Genzyme Flanders – Project Stella Genzyme Flanders – Project Stella

Genzyme Flanders – Project Stella

Geel

Foundation and Structure

Description

Building of a structure for a new production unit of Genzyme Flanders (biotechnology).

Timing

Date order 09-12-2010
Date subscription 01-09-2010
Executed by 50% Alg. Aann. Van Laere nv 50% Democo
Start 10-01-2011
Delivery 06-06-2011

Technical description

Footings, floor slabs and prefab structure.
Steel structures for outside wall and technical room.
Total area:18.000 m²
External volume:138.000 m³
Number of levels:2,5
Offices:5.000 m²
Area per level:6.000 m²

Building physical data

Excavation works:9.650 m³
Concrete:7.150 m³
Hollow core slabs:872 ton
Hollow core slabs and TT slabs:11.800 m²
Steel:589 tonnes
Frame:17.500 m²
Brickwork:2.300 m³
Industrial floors:18.000 m²