Builder:

A.S.B.L. Clinique St. Anne - St. Remi

Architect:

A.A.U.

Study team:

Bureau Franz Dupont
Clinique St. Anne – St. Remi Clinique St. Anne – St. Remi Clinique St. Anne – St. Remi Clinique St. Anne – St. Remi

Clinique St. Anne – St. Remi

Brussel

Underground car park

Description

Construction of underground car park – from ground floor to -3.
Finishing (ramps, tiling, paintwork, etc.) including technical works by subcontractor.

Timing

Date order 19-10-2010
Date subscription 10-06-2010
Executed by 100% Alg. Aann. Van Laere nv
Start 15-11-2010
Delivery 20-06-2011

Technical description

Secant piles along site perimeter.
Drainage and ground works.
Concrete structure + prefab vaulting.
Water sealing.
Total surface:2.000 m²
Gross volume:16.000 m³
Car park:8.000 m²

Building physical data

Excavation:15.000 m²
Concrete:2.500 m³
Reinforcement:166 ton
Vaulting & TT elements:4.850 m²
Steel:115 tonnes
Formwork:2.800 m²
Piles:1.850 m² + 260 anchors
Water sealing layers:2.000 m²
Poly floor:7.000 m²
Roof cladding:2.000 m²